Work to start on upgrade of Citywest roundabout

SOUTH DUBLIN County Council are due to start work on constructing the signalisation of the roundabout at the junction of Fortunestown Lane and Citywest Rd including the upgrade of pedestrian and cycle facilities last week.

It is envisaged that the works will take approximately 20 weeks.

Traffic map fortunestown lane

Traffic map at roundabout beside Citywest Shopping Centre

The normal working hours during the school holidays, within the site, will be Monday to Friday between 8am 7pm, and Saturday between 8am and 4pm, with no working on Sundays or Public Holidays.

During the school term the working hours will be similar. However, on-road works shall be limited Monday to Friday to between 9.30am and 3pm, and Saturday between 8am and 4pm, with no working on Sundays or Public Holidays.

This is to reduce the disruption to school and commuter traffic. 

The Contractor will be installing VMS signs in advance of the works to notify the public of the works. He will also be carrying out a leaflet drop to the local estates. The situation will be monitored and, if necessary, a revised traffic management plan will be considered.

Prev Family fun run to raise awareness for Spina Bifida Hydrocephalus
Next Primary school children showcase their enterprising skills through fun programme
  • Return of the flying ants!
  • Irish football supporters came out in force to remember Jack Charlton
  • Crowds gather to pay respect to former chairperson Brendan Moran
  • HSE launch Covid-19 Tracker App
  • New South Dublin County Mayor - Councillor Ed O'Brien

We use cookies to improve your experience on our site, personalise content, provide social media features, analyse our traffic, show you relevant advertising and to target and report on ads. By using the site, you consent to the use of cookies that may process personal data for these purposes.